Explore the NQ Civil Contractors portfolio showcasing our excellence in civil construction throughout Queensland. Precision and craftsmanship defines our projects, from bridge works spanning various terrains to piling works and infrastructure. Our commitment to quality is evident in each image.
Contact us to discuss your project and learn how we can help you.
Flinders Highway Strengthening & Widening – TMR
Removal and installation of 23 new culverts along the Flinders Highway.
Variation – Scrubby Creek Bridge
This Bridge is a 20m single span bridge constructed in 10 weeks to meet the specific requirements of TMR to be opened before the wet season.
Warrens Gully Pump Station – Lower Burdekin Water
Construction of a dual cell concrete pump inlet, valve pit and outlet structure, along with interconnecting MSCL piping, switch room and scour protection in the Burdekin River, North Queensland.
Approximate Contract Value $8 million
Burleigh Crossing Bridge – Richmond Shire Council
Design and Construction of a 180m span bridge to replace an existing causeway over Woolgar River, on Burleigh Yan Yean Rd, Burleigh. The project included driving of 50 x 20m piles
Approximate Contract Value $4.5 million
Mowbray River Pedestrian Bridge – Department of Industry Tourism Innovation and Development
Construction of a 6 span pedestrian bridge over Mowbray River, Port Douglas. The project included driving of 18 x 20m piles, construction of two crocodile viewing platforms and a series of pedestrian/bike ramps and pathways.
Approximate Contract value $2.8 million.
Flinders Highway Hughenden – Department of Transport & Main Roads
Replacement of 6 TMR Culvert Bridges at Hughenden. These culverts were constructed by using side-tracks to divert traffic during construction of the new structures and Road works. All redundant culverts were demolished and recycled.
Approximate Contract value $8 million with the works being completed ahead of program.
Springsure Bridges – Central Highlands Regional Council
Design and construct of 2 x single lane bridges across Meteor Creek, Springsure Rd, Rolleston. The project involved construction of 4 x abutments and wing walls, pile cap construction, construction of in situ 3 x 10m blade columns and transport and installation of 22m pre-cast decks, via 100t crawler crane.
Approximate value $3.5 million
Alderley Crossing Bridge – Flinders Shire Council
Construct of 6 span bridge across Flinders River, Dalkeith Rd, Northwest of Hughenden. Project involved construction of 14 x Ø1200 cast-in-situ piles, construction of in situ Ø1050 columns and headstocks and transport, installation and stressing of 18m pre-cast concrete deck units.
Approximate Contract value $4.3 million.
We're eager to tailor solutions to your unique needs. Call us on 0448 689 313 to share your project requirements, and let us assist you.
186A Mt Low Parkway
Mt Low, QLD 4818